"We forgot the slopes"/ Rama increases the cost of the Elbasan Qafë-Thanë road by 40 million euros

The expansion of the Elbasan-Qafë Thanë road axis continues to burden the state budget with new unforeseen costs. The Albanian Road Authority (ARRSH) has opened another tender with a limit fund of 3.5 billion lek or about 39 million euros excluding VAT for the protection and revitalization of the slopes in the Elbasan - Bushtricës Bridge segment.

Practically, this is the additional bill that Albanian citizens are paying for the stabilization of the slopes along the entire axis where the road has slipped. “These are specialized works of engineering measures and they are costly. Practically, this is the adjustment of damages from the previous work of all contractors. And this has just begun,” a source within the ARRSH told Kapital.
The reason for this gigantic procurement is openly acknowledged in the official tender documents themselves: during the drafting of the project and initial estimate for the road expansion, engineering measures for the protection of the mountain slope were not foreseen at all.
"The works for the protection of the slopes, the taking of engineering measures from Phase I to Phase VIII were unforeseen in the initial Preventive Project of the facility 'Widening the Elbasan - Qafë Thanë road'", it is stated verbatim in the ARA's Terms of Reference.
This is the second major emergency cost billed to taxpayers due to shortcomings in the design and works on this axis. Just a few months ago, after the massive landslide and damage near the Dragostunje bridge blocked traffic to the southeast, the ARRSH was forced to open another emergency procedure with the object of “Stabilization of the landslide on the Librazhd – Qafë Thanë (Dragostunje) axis” at a cost of 27 million euros.
From "forgetfulness" to a road safety emergency
To open the new 4-lane route along the Shkumbini Valley, massive excavations were carried out on the mountain slope, leaving behind bare escarpments up to 60 meters high. Without any engineering protection or drainage system, the situation in the first 27.6 kilometers of the axis is already described by the authorities themselves as “critical”.

According to ARRSH documents, this negligence is producing daily consequences on the ground. Stones and rock blocks that break away from heights fall onto the road, damage signage and sidewalks, occasionally block traffic and directly endanger the lives of drivers.
Furthermore, the excavations have stripped the mountain of its natural counterweight, so whenever it rains, water seeps into the cracks in the rock and increases the risk of sudden landslides. All this is accompanied by severe environmental degradation, where the slopes, stripped of vegetation, have become an “open wound” to erosion.
To remedy this shortcoming of the initial design, the ARRSH seeks to contract a company or consortium of operators through a “turnkey” contract. This means that the winner will undertake both the geological-geotechnical studies and implementation design (within 3 months), as well as the complete construction of the protective works for approximately 200,000 m² of slopes (within 8 months).
Interventions will include covering slopes with steel mesh, fixing with rock bolts, installing dynamic rockfall barriers, retaining walls, drainage channels and hydroseeding.
The procurement procedure was opened on November 24, 2026 and the bids will close on December 28, 2026, thus adding another cost of tens of millions to the Corridor VIII project.
Budget monster
The expansion of the Elbasan-Qafë Thanë road is rapidly turning into a bottomless pit for citizens' money. Official budget documents show that the costs of this work have spiraled out of control, inflated by constant contract modifications, poor management, and geological emergencies along the road.

What started as a step-by-step project has so far reached a bill of 35.2 billion lek, or over 387.8 million euros.
But this is not the end of the world. It is likely that the bill for the 51-kilometer road will significantly exceed 700 million euros, as contracts increase year by year./ kapitali.al
Po ndodh...
May 9th Elections REFERENDUM against the System
ide
Hostage parties, hostage politics, hostage Albania!
Elisa and the dilemma of Rama's political legacy!
The eunuchs of power have everything but the courage for dignity.
top
receta Alfa
TRENDING 
shërbime
- POLICIA129
- POLICIA RRUGORE126
- URGJENCA112
- ZJARRFIKESJA128